UPDATE: Roadwork This Week in Morristown

Plan your routes accordingly.

The town released a list of upcoming road improvement projects and their expected timelines Monday afternoon, as well as notice of a "seepage control project" for Pocahontas Dam. Plan your routes accordingly.

This list of projects runs through the end of this week. However, the Pocahontas Dam project is listed as "to project completion."

All projects subject to schedule changes because of weather conditions.

Monday, Tuesday, 10/22-23/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location:  Abbett Avenue (Ridgedale Avenue to Martin Luther King) – roadway milling and manhole replacement
  • Work Hours: 7 a.m. to 4 p.m.
  • Special Conditions: Through traffic from Martin Luther King will be permitted until 9 a.m. Complete or partial road closure after 9 a.m.

Tuesday, 10/23/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location: Mills Street (Washington Street to Sussex Turnpike) - roadway milling and manhole replacement
  • Work Hours: 7 a.m. to 6 p.m.
  • Special Conditions: Through traffic will be permitted until 9 a.m.  Complete or partial road closure after 9 a.m.

Wednesday, 10/24/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location: Abbett Avenue (Ridgedale Avenue to Martin Luther King) – roadway paving
  • Work Hours: 9 a.m. to 4:30 p.m.
  • Special Conditions: Road Closure for paving

Wednesday, 10/24/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location:  Town Hall Turn Around - milling
  • Work Hours: 7 a.m. to 4 p.m.
  • Special Conditions: Access to rear of Town Hall at all times during      construction

Wednesday, 10/24/2012

  • Project: Manhole Casting Replacement
  • Contractor: Jo Med Contracting
  • Work      Location: Mills Street (Washington Street to Sussex Turnpike) – Manhole replacement and resets
  • Work Hours: 9 a.m. to 4 p.m.
  • Special Conditions: No road closures

Thursday, 10/25/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location:  Abbett Avenue (Martin Luther King to Ridgedale Avenue) – finish roadway paving
  • Work Hours: 9 a.m. to 4:30 p.m.
  • Special Conditions: Road closure for paving

Thursday, 10/25/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location: Mills Street (Washington Street to Sussex Turnpike) - start roadway paving
  • Work  Hours: 9 a.m. to 5:30 p.m.
  • Special Conditions: Road closure for paving

Thursday, 10/25/2012

  • Project: Roadway Traffic Striping
  • Contractor: Denville Line
  • Work Location: Abbett Avenue (Martin Luther King to Ridgedale Avenue) –  roadway striping (completed portion)
  • Work Hours: 9 a.m. to 4 p.m.
  • Special Conditions: Minor delays

Friday, 10/26/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location: Mills Street (Washington Street to Sussex Turnpike) - finish roadway paving
  • Work Hours: 9 a.m. to 5:30 p.m.
  • Special Conditions: Road closure for paving

Friday 10/26/2012

  • Project: Roadway Traffic Striping
  • Contractor: Denville Line
  • Work Location: Abbett Avenue (Martin Luther King to Ridgedale Avenue) – finish roadway striping
  • Work Hours: 9 a.m. to 4 p.m.
  • Special Conditions: Minor delays

Friday, 10/26/2012

  • Project: Roadway Traffic Striping
  • Contractor: Denville Line
  • Work Location: Mills Street (Washington Street to Sussex Turnpike) - roadway striping (completed portion)
  • Work Hours:  9 a.m. to 4 p.m.
  • Special Conditions: Minor delays

Friday 10/26/2012

  • Project: Roadway Milling and Paving
  • Contractor: Tilcon New York, Inc., Morris County Co-Op Contract #6
  • Work Location: Town Hall Turn Around - paving
  • Work Hours:  7 a.m. to 4 p.m.
  • Special Conditions: Driveway Closure

Tuesday, 10/23/2012 to Project Completion (Fall 2012)

  • Project: Pocahontas Dam Seepage Control Project
  • Contractor: Diaco Heavy Construction
  • Work Location: Pocahontas Dam – Steel sheeting, concrete work and stream stabilization
  • Work Hours: 7 a.m. to 4 p.m.

Updated: Additional roadwork times and locations added.

Chris October 23, 2012 at 04:54 PM
Awesome! They should put this out ever Friday for the next week's schedule of road closures.
Chris October 23, 2012 at 04:56 PM
And how about an update for the 287 traffic??? John, you should do an article about the MASSIVE traffic it is causing.
Jeff Grayzel October 23, 2012 at 05:14 PM
This schedule is incorrect. Abbett Avenue was milled on Monday.
John Dunphy October 23, 2012 at 07:53 PM
Hi, Jeff. I checked with the Administrator's office here in Morristown and someone there said the project was happening over two days. It was milled Monday, and supposed to be paved Tuesday.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »